Our Lady of Namulenga High School Project

WORK PROGRESS

Work continues on the Our Lady of Namulenga High School campus. Below is a detail of ongoing construction work.

SUBSTRUCTURE

Jump to a structure
    Add a header to begin generating the table of contents
    ADMNISTRATION BLOCK
    • Setting out……………………. 100%
    • Excavation…………………….  100%
    • Sand blinding and levelling………………. 100%
    • Underground beam rebars fabrication 50%
    TTEOLNPROGRESSREPORTJULY14-1
    MULTIPURPOSE HALL
    • Setting out……………………. 100%
    • Excavation and cleaning…………………….  85%
    TTEOLNPROGRESSREPORTJULY14-2
    WESTERN CLASSROOMS (2No)
    • Setting out…………………………100%
    • Excavations……………………….75%
    • Levelling…………………………...50%
    TTEOLNPROGRESSREPORTJULY14-3
    TTEOLNPROGRESSREPORTJULY14-4
    WESTERN LABORATORY (1No)
    • Setting………………………... 100%
    • Excavations…………………. 65%
    TTEOLNPROGRESSREPORTJULY14-5
    WESTERN PAVILIONS (2No)
    • Setting………………………... 100%
    • Levelling………………………50%
    • Excavations………………….70%
    TTEOLNPROGRESSREPORTJULY14-6
    TTEOLNPROGRESSREPORTJULY14-7
    EASTERN CLASSROOMS (2 No)
    • Setting out…………………….100%
    • Levelling………………………45%
    • Excavations……………………70%
    TTEOLNPROGRESSREPORTJULY14-8
    TTEOLNPROGRESSREPORTJULY14-9
    EASTERN LABORATORY (1 No)
    • Setting out…………………………….100%
    • Excavations and cleaning…………….45%
    TTEOLNPROGRESSREPORTJULY14-10
    2 EASTERN PAVILIONS
    • Setting out…………………………….. 95%
    • Excavations ………………………….. 50%
    TTEOLNPROGRESSREPORTJULY14-11
    TTEOLNPROGRESSREPORTJULY14-12
    LIBRARY
    • Setting out………………………………. 100%
    • Excavation………………………………  60%
    TTEOLNPROGRESSREPORTJULY14-13
    TTEOLNPROGRESSREPORTJULY14-14
    WESTERN HOSTELS (3 No)
    • Setting out……………………………….   45%
    STAFF HOUSES
    • Setting out………………………………….80%
    TTEOLNPROGRESSREPORTJULY14-15
    HEAD MASTERS AND TEACHERS HOUSE (6No)
    • Setting out…………………………….   100%
    • Excavations and cleaning……………...   30%
    TTEOLNPROGRESSREPORTJULY14-16
    TTEOLNPROGRESSREPORTJULY14-17
    STRUCTURES BEING SET OUT NOW
    • EASTERN HOSTELS (3No) 
    • THE CLOCK TOWER