Our Lady of Namulenga High School Project
WORK PROGRESS
Work continues on the Our Lady of Namulenga High School campus. Below is a detail of ongoing construction work.
SUBSTRUCTURE
Jump to a structure
Add a header to begin generating the table of contents
ADMNISTRATION BLOCK
- Setting out……………………. 100%
- Excavation……………………. 100%
- Sand blinding and levelling………………. 100%
- Underground beam rebars fabrication 50%

MULTIPURPOSE HALL
- Setting out……………………. 100%
- Excavation and cleaning……………………. 85%

WESTERN CLASSROOMS (2No)
- Setting out…………………………100%
- Excavations……………………….75%
- Levelling…………………………...50%


WESTERN LABORATORY (1No)
- Setting………………………... 100%
- Excavations…………………. 65%

WESTERN PAVILIONS (2No)
- Setting………………………... 100%
- Levelling………………………50%
- Excavations………………….70%


EASTERN CLASSROOMS (2 No)
- Setting out…………………….100%
- Levelling………………………45%
- Excavations……………………70%


EASTERN LABORATORY (1 No)
- Setting out…………………………….100%
- Excavations and cleaning…………….45%

2 EASTERN PAVILIONS
- Setting out…………………………….. 95%
- Excavations ………………………….. 50%


LIBRARY
- Setting out………………………………. 100%
- Excavation……………………………… 60%


WESTERN HOSTELS (3 No)
- Setting out………………………………. 45%
STAFF HOUSES
- Setting out………………………………….80%

HEAD MASTERS AND TEACHERS HOUSE (6No)
- Setting out……………………………. 100%
- Excavations and cleaning……………... 30%


STRUCTURES BEING SET OUT NOW
- EASTERN HOSTELS (3No)
- THE CLOCK TOWER