Progress Report – July 28, 2023

WORK PROGRESS

Work continues to progress. Unfortunately, there is currently an economic crisis prevailing in Malawi – fuel shortages. This has resulted in costs/prices of goods and services to skyrocket.

This situation has affected the progress of on-going work on site. The contractor is unable to utilize the back-hoe machines to aid in the excavation process, thus resorting to manual digging. That notwithstanding, considerable progress is being made as the morale of the workers on site is very high.

SUBSTRUCTURE

Jump to a Substructure
    Add a header to begin generating the table of contents
    ADMNISTRATION BLOCK
    • Setting out……………………. 100%
    • Excavation……………………. 100%
    • Sand blinding and levelling………………. 100%
    • Underground beam rebars fabrication 50%
    TTEOLNPROGRESSREPORTJULY14-1
    MULTIPURPOSE HALL
    • Setting out……………………. 100%
    • Excavation and cleaning…………………….  85%
    TTEOLNPROGRESSREPORTJULY14-2
    WESTERN CLASSROOMS (2No)
    • Setting out…………………………100%
    • Excavations……………………….75%
    • Levelling…………………………...50%
    TTEOLNPROGRESSREPORTJULY14-3
    TTEOLNPROGRESSREPORTJULY14-4
    WESTERN LABORATORY (1No)
    • Setting………………………... 100%
    • Excavations…………………. 65%
    TTEOLNPROGRESSREPORTJULY14-5
    WESTERN PAVILIONS (2No)
    • Setting………………………... 100%
    • Levelling………………………50%
    • Excavations………………….70%
    TTEOLNPROGRESSREPORTJULY14-6
    TTEOLNPROGRESSREPORTJULY14-7
    EASTERN CLASSROOMS (2 No)
    • Setting out…………………….100%
    • Levelling………………………45%
    • Excavations……………………70%
    TTEOLNPROGRESSREPORTJULY14-8
    TTEOLNPROGRESSREPORTJULY14-9
    EASTERN LABORATORY (1 No)
    • Setting out…………………………….100%
    • Excavations and cleaning…………….45%
    TTEOLNPROGRESSREPORTJULY14-10
    2 EASTERN PAVILIONS
    • Setting out…………………………….. 95%
    • Excavations ………………………….. 50%
    TTEOLNPROGRESSREPORTJULY14-11
    TTEOLNPROGRESSREPORTJULY14-12
    LIBRARY
    • Setting out………………………………. 100%
    • Excavation………………………………  60%
    TTEOLNPROGRESSREPORTJULY14-13
    TTEOLNPROGRESSREPORTJULY14-14
    WESTERN HOSTELS (3 No)
    • Setting out……………………………….   45%
    STAFF HOUSES
    • Setting out………………………………….80%
    TTEOLNPROGRESSREPORTJULY14-15
    HEAD MASTERS AND TEACHERS HOUSE (6No)
    • Setting out…………………………….   100%
    • Excavations and cleaning……………...   30%
    TTEOLNPROGRESSREPORTJULY14-16
    TTEOLNPROGRESSREPORTJULY14-17
    STRUCTURES BEING SET OUT NOW
    • EASTERN HOSTELS (3No) 
    • THE CLOCK TOWER