UPDATE – Progress Report – January 26, 2024

SUBSTRUCTURE

Jump to a Substructure
    Add a header to begin generating the table of contents

    Client
    TTE/ Diocese of Joliet

    Consultant
    Team Lift Inc.

    Contractor
    Sitbec Ltd

    Proposed Contract Period
    80 weeks

    Proposed Commencement Date
    2nd January, 2023

    Proposed Completion Date
    2nd July, 2024

    Time Elapsed
    55weeks

    Elapsed time percentage
    68.75%

    Overall progress percentage
    39.5%

    Brief: SUPERSTRUCTURE BLOCK WORK IN PROGRESS EXCEPT FOR HOSTELS AND THE LIBRARY

    ADMNISTRATION BLOCK

    SUPERSTRUCTURE BLOCKWORK CONTINUES

    PROJECT-PROGRESS-UPDATE-JAN-24-2
    MULTIPURPOSE HALL

    SUPERSTRUCTURE BLOCKWORK AND BASEMENT WORKS CONTINUES

    PROJECT-PROGRESS-UPDATE-JAN-24-3
    CLASSROOMS (4No)

    SUPERSTRUCTURE BLOCKWORK AND BASEMENT WORKS CONTINUES

    PROJECT-PROGRESS-UPDATE-JAN-24-4
    PAVILLIONS (4 No)

    SETTING OF SUPERSTRUCTURE PILLARS

    PROJECT-PROGRESS-UPDATE-JAN-24-5
    LABORATORY (2 No)

    SUPERSTRUCTURE WALL BLOCKWORK CONTINUES

    PROJECT-PROGRESS-UPDATE-JAN-24-6
    LIBRARY

    CONCRETE SLAB CASTING CONTINUES

    PROJECT-PROGRESS-UPDATE-JAN-24-7
    STAFF HOUSES (3 No)

    SUPERSTRUCTURE WALL BLOCKWORK CONTINUES

    PROJECT-PROGRESS-UPDATE-JAN-24-8
    HOSTELS (6 No)

    CONCRETE SLAB CASTING IN PROGRESS

    PROJECT-PROGRESS-UPDATE-JAN-24-9
    HEADMASTER, TEACHERS HOUSES

    SUPERSTRUCTURE WALL BLOCKWORK

    PROJECT-PROGRESS-UPDATE-JAN-24-11
    CAFETERIA

    SUPERSTRUCTURE BLOCKWORK IN PROGRESS

    PROGRESS-REPORT----1-DEC-23-10
    OTHER PICTURES
    Figure 1 eastern classroom section
    Figure 1 eastern classroom section
    Figure 4. Eastern side hostels
    Figure 4. Eastern side hostels
    PROJECT-PROGRESS-UPDATE-JAN-24-18
    PROJECT-PROGRESS-UPDATE-JAN-24-21
    Figure 2. superstructure wall blockwork (teachers houses)
    Figure 2. superstructure wall blockwork (teachers houses)
    Figure 5. site view
    Figure 5. site view
    PROJECT-PROGRESS-UPDATE-JAN-24-19
    PROJECT-PROGRESS-UPDATE-JAN-24-22
    Figure 3. staff houses
    Figure 3. staff houses
    Figure 6. site middle section view
    Figure 6. site middle section view
    PROJECT-PROGRESS-UPDATE-JAN-24-20