UPDATE – Progress Report – September 21, 2023
SUBSTRUCTURE
Jump to a Substructure
Add a header to begin generating the table of contents
ADMNISTRATION BLOCK
- FOUNDATION BLOCK WORK COMPLETED
- SOIL BACK FILLING AND COMPACTION, ANT TREATMENT IN PROGRESS
- IN READINESS FOR THE REINFORCED CONCRETE FLOOR SLAB

MULTIPURPOSE HALL
- FOUNDATION BLOCK WORK IN PROGRESS

CLASSROOMS (4No)
- FOUNDATION BLOCK WORK IN PROGRESS

PAVILLIONS (4 No)
- FOUNDATION BLOCK WORK COMPLETE

LABORATORY (2 No)
- FOUNDATION BLOCK WORK COMPLETE

LIBRARY
- FOUNDATION EXCAVATION IS IN PROGRESS
(Delayed Structural Details)

STAFF HOUSES (3 No)
- FOUNDATION CONCRETE FOOTING COMPLETED & FOUNDATION BLOCK WORK IN PROGRESS

HEADMASTER, TEACHERS HOUSES
- FOUNDATION CONCRETE FOOTING COMPLETED & FOUNDATION BLOCK WORK IN PROGRESS

OTHER WORKS
- LAVATORY
- Excavation and cleaning… 100%
- Footing………… 100%
- Foundation blockwork…… 100%
- BLOCK MOULDING
- we have produced 43445 Blocks since we started - BORROW PITS
- Clearing and top soil removal
- For Gravel fill on the structure - REINFORCEMENT BAR
- Cutting and bending for hostel ground beams in progress