UPDATE – Progress Report – September 21, 2023

SUBSTRUCTURE

Jump to a Substructure
    Add a header to begin generating the table of contents
    ADMNISTRATION BLOCK
    • FOUNDATION BLOCK WORK COMPLETED
    • SOIL BACK FILLING AND COMPACTION, ANT TREATMENT IN PROGRESS
    • IN READINESS FOR THE REINFORCED CONCRETE FLOOR SLAB
    administration-block-092123
    MULTIPURPOSE HALL
    • FOUNDATION BLOCK WORK IN PROGRESS
    multipurpose-hall-092123
    CLASSROOMS (4No)
    • FOUNDATION BLOCK WORK IN PROGRESS
    classrooms-4no-092123
    PAVILLIONS (4 No)
    • FOUNDATION BLOCK WORK COMPLETE
    pavillions-4-no-092123
    LABORATORY (2 No)
    • FOUNDATION BLOCK WORK COMPLETE
    labratory-2-no-092123
    LIBRARY
    • FOUNDATION EXCAVATION IS IN PROGRESS
      (Delayed Structural Details)
    library-092123
    STAFF HOUSES (3 No)
    • FOUNDATION CONCRETE FOOTING COMPLETED & FOUNDATION BLOCK WORK IN PROGRESS
    staff-hjouses-3-no-092123
    HEADMASTER, TEACHERS HOUSES
    • FOUNDATION CONCRETE FOOTING COMPLETED & FOUNDATION BLOCK WORK IN PROGRESS
    headmasster-teacher-homes-092123
    OTHER WORKS
    1. LAVATORY
      - Excavation and cleaning… 100%
      - Footing………… 100%
      - Foundation blockwork…… 100%
    1. BLOCK MOULDING
      - we have produced 43445 Blocks since we started
    2. BORROW PITS
      - Clearing and top soil removal
      - For Gravel fill on the structure
    3. REINFORCEMENT BAR
      - Cutting and bending for hostel ground beams in progress
    other-works-1-092123
    other-works-3-092123
    other-works-2-092123